ParticipantHi Sky,
I’ve updated Events Calendar to 4.6.17 in the staging version.
Thnaks for your support!
gesine
ParticipantGuten Morgen 🙂
thanks for the information. I’m excited to hear the results.
Ebenfalls schöne Tage!
gesine
ParticipantHi Sky,
I’ve done the update. Unfortunately, as far as I can see, it doesn’t change anything regarding our issue… That would have been great!
Thanks for your further investigation! Can I now uninstall WP staging or do you still need it?
gesine
ParticipantThis reply is private.
gesine
ParticipantHi Sky,
in the staging page the URL title form is: https://gymnasium-meine.de/staging?post_type=tribe_events
On the main page the URL slug should be “kalender”
Is this what you meant? I hope it helps you solving the issue.
Thanks in advance!
gesine
ParticipantHi Sky,
please ignore what I have wrote in my previuos post about the staging version of the calendar. You can take a look at it here: https://gymnasium-meine.de/staging/&post_type=tribe_events&eventDisplay=month&tribe-bar-date=2018-05&post_type=tribe_events&eventDisplay=month&tribe-bar-date=2018-05
gesine
ParticipantHi Andras,
I cannot tell you when exactly these events have been imported. But as they are events planned for a long time I assume the should have been imported together with the other events for the whole year in February/March (I don’t remember when exactly I installed the plugin extension for Gcal imports).
But I was successful with deleting both of the events manually and importing them anew. Now they have the correct date. By the way: Sorry, but my client gave me the wrong dates: It is 2nd – 4th MAY and 6th – 11th MAY (not Arpil as written in my previous post).
Now I know a solution to handle these wrong imports manually at least. But please let me know if you have a basic solution for this issue that prevents similars errors in the future.
Thanks and sunny regards!
gesine
ParticipantThis reply is private.
gesine
ParticipantThis reply is private.
gesine
ParticipantHi András,
now I haven’t heard of you for two weeks already. How about the Problem of importing events?
My client just told me that meanwhile there are new errors:
E. g. “Lateinfahrt” should last from 2nd – 4th April (due to google Cal) but occurs in events calendar from 4th – 6th April.
Another issue: “Spanienaustausch” should take place from 6th – 11th April but is set to 11th – 16th April in events calendar.
Regarding these new issues it is likely that during the import the end of the original date is set as beginning for the fals date whereas the duration remains the same. Please check again and let me know how we can solve the issue!
Best regards!
gesine
ParticipantThis reply is private.
gesine
ParticipantThis reply is private.
gesine
ParticipantHi Sky,
I’ve tested to activate Twenty Seventeen but it didn’t have any effect on the problem. What else can I do?
Best regards!
gesine
ParticipantDear Andras,
thanks for your post. Could you explain to me what exactly you are waiting for? I mean what else do you need to find the solution for the wrongly imported event? Can I provide any further informaiton?
I am asking because my client would like to know what went wrong and how to improve upcoming imports in order to avoid any further issues.
Thanks for a short reply in advance! Have a good day!
Gesine
gesine
ParticipantHi Andrà s,
yes, you are right! The event was in the ignored list and I managed to unignore it. Until you told me about I didn’t even know of this list!
I’ll wait for further results of your investigation! Thanks for taking this issue serious!